Pan Yue, deputy director of the State Environmental Protection Administration, notified 30 illegal construction projects and pointed out that we should resolutely stop the construction of illegal construction projects regardless of the environmental impact assessment system.

Pan Yue, deputy director of the State Environmental Protection Administration, announced in Beijing on January 18 that the construction of 30 illegal construction projects in 13 provinces and cities, including the Xiluodu Hydropower Station on the Jinsha River, should be suspended, and pointed out that environmental protection laws and regulations should be strictly enforced, environmental access should be strictly enforced, and low-level repeated construction and disorderly construction should be completely curbed, Illegal construction projects such as tepex reinforced DLFT polypropylene material equivalent to glass felt reinforced or glass fiber fabric reinforced polypropylene matrix thermoplastic system (GMT and gmtex) iron are never allowed. It is reported that this is also the first large-scale announcement of illegal construction projects by the State Environmental Protection Administration after the implementation of the Environmental Impact Assessment Law of the people's Republic of China

Pan Yue said that with the rapid development of the national economy, investment in fixed assets has increased. Some local governments and enterprises ignored the laws of national economic development and environmental protection requirements, and started a number of construction projects without authorization. Recently, the State Environmental Protection Administration found that some enterprises had serious environmental violations in the process of accepting the environmental impact assessment of construction projects. The construction of the project was started without the approval of the environmental protection department, which seriously violated the relevant provisions of the environmental impact assessment law and the regulations on the administration of environmental protection of construction projects

according to panyue, the Environmental Impact Assessment Law of the people's Republic of China stipulates that the approval department of a construction project shall not approve its construction and the construction unit shall not start construction without the approval of the environmental impact assessment document of the construction project. The construction projects that have been exposed and suspended this time have been started without the approval of the EIA report, and some projects have been basically completed, which are typical illegal projects that were built before approval. The State Environmental Protection Administration has decided to order the immediate suspension of the construction of these projects and impose penalties according to law. For the direct personnel, it is suggested that the relevant departments should give administrative sanctions according to law

Pan Yue stressed that environmental impact assessment is a serious legal system. By implementing the environmental impact assessment system, we can avoid exceeding the bearing capacity of natural resources and environment due to blind project construction and disorderly economic development, which can make the layout of production factors and the allocation of productivity more scientific and reasonable, and the operation of the national economy more healthy and orderly. While strictly enforcing environmental protection laws and regulations, resolutely stopping the construction of illegal projects that ignore the environmental impact assessment system, and completely curbing the phenomenon of low-level repeated construction, the State Environmental Protection Administration will continue to reform and improve the environmental impact assessment and the "three Simultaneities" system (the environmental protection facilities in the construction project must be designed, constructed, and put into operation simultaneously with the main project), and effectively promote the strategic transformation of the development model, Promote the coordination between China's economy, society and environment 1 Vanadium industry pattern development

first, the torque to promote the engine refers to the torque output from the crankshaft end of the engine to carry out strategic environmental impact assessment, and establish and improve the comprehensive decision-making mechanism for environment and development. To realize the environmental protection policy of "prevention first", we must prevent the decision-making mistakes and environmental damage of major economic development activities at a high level. A single environmental impact assessment of construction projects is not enough to comprehensively protect the environment and make sustainable use of resources. We should carry out environmental impact assessment of major economic development and development planning, control new pollution and ecological damage from the source, and coordinate the relationship between economic development, social progress and environmental protection

second, promote the development of circular economy, promote the adjustment of economic structure and the transformation of economic growth mode. Circular economy is an important carrier of new industrialization, a strategic choice for the current transformation of development mode, and reflects the requirements of the scientific concept of development. China has a large population, few resources and a fragile ecological environment. The contradiction between economic growth and resources and environment is very prominent. Environmental impact assessment and the "three Simultaneities" system are important means to promote the development strategy of circular economy. The implementation of circular economy should be promoted in the environmental impact assessment of construction projects and planning and the "three Simultaneities" management

third, strictly administer according to law and resolutely punish illegal acts. In accordance with the relevant provisions of the State Council on curbing blind investment in some industries and the requirements of macroeconomic regulation and control policies, we should strengthen the investigation and punishment according to law, and resolutely curb the momentum of violating the national industrial policies and macroeconomic regulation and control regulations, blind investment and illegal construction. The environmental protection department that fails to perform the supervision and management duties according to law and fails to investigate, deal with or report the illegal acts of the construction project must investigate the administrative responsibility of the relevant leaders and relevant persons. At the same time, we should strengthen the "three Simultaneities" acceptance and strengthen the "three Simultaneities" law enforcement inspection. Those who fail to apply for environmental protection acceptance on time shall be notified in time, and those who fail to do so within the time limit shall be punished according to law; Those who fail to pass the acceptance shall be stopped from production or use according to law and punished

fourth, improve and perfect the public participation mechanism and give full play to the role of public participation. The number of construction projects is huge, and it is obviously not enough to rely on the government to supervise them. It is an important way to improve the effectiveness of the two systems by mobilizing social groups and the public to participate in the process of environmental impact assessment and "three Simultaneities" management, and making the public become a basic force influencing environmental impact decision-making in the form of hearings and discussions. It can also make up for the deficiencies of environmental impact assessment and "three Simultaneities" supervision, and ensure the scientificity of decision-making

fifth, strictly supervise the evaluation team, implement the professional qualification system, and strengthen the investigation. On the basis of regular assessment every two years, we will increase the number of centralized spot checks every year. We will strengthen the daily supervision of certified units of environmental impact assessment, strictly enforce the qualification access conditions of environmental impact assessment units, and refine the assessment indicators and punishment measures. Improve the competition mechanism, introduce overseas environmental impact assessment institutions, participate in the domestic environmental impact assessment market, and improve the level of environmental impact assessment in China

Pan Yue finally said that the State Environmental Protection Administration will resolutely investigate illegal construction projects by stages according to the law, deal with them one by one, deal with them one by one, and never allow illegal construction projects like Tieben. The State Environmental Protection Administration will inspect and spot check these suspended projects from time to time, and timely publish the relevant information to the public

appendix:

construction unit and name of illegal construction project notified by the State Environmental Protection Administration

serial number construction unit name of illegal construction project

1 China Three Gorges Project Development Corporation Jinsha River Xiluodu Hydropower Station (12600mw)

2 China Three Gorges Project Development Corporation Three Gorges underground power station (total installed capacity 4200mw)

3 Three Gorges power station of China Three Gorges Project Development Corporation (with a total installed capacity of 100MW)

4 taicanggang environmental protection power generation Co., Ltd. Jiangsu taicanggang environmental protection power generation Co., Ltd. phase IV 2 × 600MW expansion project

5 Xuzhou Huaxin Power Generation Co., Ltd. Jiangsu Xuzhou power plant expansion 2 × 300MW project

6 Jiangsu Xutang Power Generation Co., Ltd. Xutang Power Generation Co., Ltd. 2 × 300MW unit expansion project

7 Jiangyin Xiagang power plant 2 of Jiangyin Sulong Power Generation Co., Ltd × 330MW unit expansion project

8 it is worthwhile for Jiangsu to make some changes to this end. Huadian Yangzhou Power Generation Co., Ltd. Yangzhou Power Generation Co., Ltd. heating expansion 2 × 300MW project

9 Xiamen Huaxia International Power Development Co., Ltd. Xiamen Songyu Power Plant Phase II 2 × 300MW expansion project

10 Baotou Donghua Thermal Power Co., Ltd. Baotou Donghua Thermal Power Co., Ltd. 2 × 300MW project heating unit

11 Jingyuan first power generation Co., Ltd. Gansu Jingyuan Power Plant Phase III 2 × 300MW expansion project

12 Ningxia Malian power plant 2 of Ningxia Power Generation Group Co., Ltd × 330MW project

13 Jiangsu Xinhai Power Generation Co., Ltd. Jiangsu Xinhai Power Generation Co., Ltd. 2 × 300MW heating unit expansion project

14 Datang International Co., Ltd. Zhejiang Datang Wushashan power plant 4 × 600MW new project

15 Inner Mongolia Huolinhe Power Generation Co., Ltd. Inner Mongolia Huolinhe Power Generation Co., Ltd. 2 × 300MW new project

16 Qufu Shengcheng Thermal Power Co., Ltd. Qufu Shengcheng Thermal Power Co., Ltd. 2 × 200MW cogeneration project

17 Sichuan Nanchong Wanxian 500kV power transmission and transformation project of Sichuan Electric Power Co., Ltd.

18 Sichuan Guang'an Nanchong 500kV power transmission and transformation project of Sichuan Electric Power Co., Ltd.

19 Fujian electric power Xiamen and Jinjiang substations and other 500kV transmission and transformation projects of Fujian electric power company

20 Ningxia Shizuishan Power Plant of China Guodian Corporation 2 × 330MW technical transformation project

21 Guizhou Dafang power plant of China Huadian Corporation 4 × 300MW new project

22 Xuanwei Power Plant Phase VII of Guodian Xuanwei Power Generation Co., Ltd. 2 × 300MW expansion project

23 Henan Zhongfu Industrial Co., Ltd. Henan Zhongfu Industrial Co., Ltd. 2 × 300MW expansion project

24 Inner Mongolia Xinfeng Thermal Power Co., Ltd. Inner Mongolia Xinfeng Thermal Power Co., Ltd. 2 × 300MW heat supply unit new project

25 Inner Mongolia Zhungeer dafanpu power plant Inner Mongolia Zhungeer dafanpu power plant 2 × 300MW unit new construction project

26 Nanjing Suyuan Thermal Power Co., Ltd. Nanjing Suyuan thermal power phase II project 2 × 300MW power generation and heating unit

27 China National Petroleum Corporation Lanzhou Petrochemical Company 1.2 million ton/year delayed coking unit project

28 Foshan Huafeng Paper Co., Ltd. increased capital to build a new 300000 ton/a high-grade coated whiteboard project in a different place

29 Dandong Lhasa National Highway Dengkou Balagong section (including Dengkou Yellow River Bridge) project of the Department of transportation of Inner Mongolia Autonomous Region

30 Fuzhou Development and Reform Commission Flood control project on the South Bank of Minjiang north port in Fuzhou and Nanjiang binlu Road Project